After leveling resources assign 4 units of lumber to Task A and 3 units of lumber to Task D. Each unit of lumber costs $500/unit. Carpenter labor is $100/hr. What is the total cost of the project?

a)$23,200

b)$24,700

c) $25,200

d)$26,700"

User Miles
by
8.6k points

1 Answer

2 votes

Final answer:

To find the total cost of the project, calculate the cost of lumber for each task and add them together. Additional information is needed to calculate the cost of carpenter labor.

Step-by-step explanation:

To calculate the total cost of the project, we need to find the cost of lumber and the cost of carpenter labor.

For Task A, 4 units of lumber are assigned, which will cost 4 x $500 = $2000.

For Task D, 3 units of lumber are assigned, which will cost 3 x $500 = $1500.

The total cost of lumber is $2000 + $1500 = $3500.

As for carpenter labor, we need more information on the number of hours worked for each task and the cost per hour to calculate the cost. Once we have that information, we can add it to the total cost of lumber to find the total cost of the project.