The current course module addressed the knowledge area of project schedule management. Please locate this knowledge area on the framework (find the document in the resources section of Module 1) and select all the processes that belong to it from the following list.

A) Initiation.
B) Planning.
C) Execution.
D) Monitoring and Controlling.

User AmdY
by
7.7k points

1 Answer

5 votes

Final answer:

Project schedule management is a knowledge area in project management that belongs to the planning phase. It involves processes like defining activities, sequencing activities, estimating activity durations, and developing schedule.

Step-by-step explanation:

The knowledge area of project schedule management can be found in the Project Management Institute (PMI) framework. Within this framework, project schedule management is a part of the planning phase of a project. It involves several processes that help in creating, implementing, and controlling the project schedule.

The processes that belong to project schedule management are:

  • Define Activities
  • Sequence Activities
  • Estimate Activity Durations
  • Develop Schedule

These processes are carried out during the planning phase to ensure that the project has a well-defined schedule that is achievable and helps in completing the project on time.