The Wilsons hired Gary to build an addition onto their house in Minnesota. Gary subcontracted out the electrical work to Oliver. Within how many days must Gary and Oliver deliver lien notices to the Wilsons?

A. 45 days
B. 120 days
C. 180 days
D. 10 days

User Philsch
by
8.2k points

1 Answer

1 vote

Final answer:

In Minnesota, both Gary and Oliver must deliver lien notices to the Wilsons within 45 days.

Step-by-step explanation:

In Minnesota, both Gary and Oliver must deliver lien notices to the Wilsons within 45 days. This is required under the state's mechanic's lien laws. This notice informs the property owner that the subcontractor has done work on the property and may claim a lien on it if they are not paid.