Final answer:
If Master sues Accur under the liquidated damage provision of the contract, Master will recover $2,000 from Accur.
Step-by-step explanation:
If Master sues Accur under the liquidated damage provision of the contract, Master will recover $2,000 from Accur.
The liquidated damages clause in the contract stated that Accur pays $1,000 to Master for each day that Accur was late in responding to a service request. Accur was notified on January 12 and did not respond until January 15, which is a delay of 3 days. Therefore, Master can recover $1,000 for each day of delay, totaling $2,000.
The correct answer is C) Recover $2,000 from Accur.