Explanation:2. Bacha construction company contracted to build a municipal warehouse for the city of Adama for BR 5,200,000. The construction began on February 2,2008 and completed in 2010.the company uses percentage of accounting records of the company in relation to this contract :
2008 2009 2010
Total estimated cost of the contract br 4,000,000 br4,160,000 br4,200,000
Cumulative gross profit recognized 330,000 700,000 ?
Instruction
(a) Compute the construction costs incurred in each of the year 2008,2009 ,& 2010.
(b) Compute the contract revenue and gross profit recognized in each of the year 2008,2009,& 2010