Final answer:
To find the second region's over or under budget amount, subtract the first region's overage ($36,236) from the total overage ($50,615). The result is that the second region is over budget by $14,379.
Step-by-step explanation:
If the Piano Company's costs were over budget by $50,615, and the first region's costs were over budget by $36,236, we can determine the second region's over or under budget amount by subtracting the first region's overage from the total overage.
To calculate:
- Total overage for both regions = $50,615
- First region's overage = $36,236
- Second region's overage = Total overage - First region's overage
- Second region's overage = $50,615 - $36,236
- Second region's overage = $14,379
The second region's costs were over budget by $14,379.