33.5k views
4 votes
A and B can do a work in 20 days. When A works at 60% capacity, B has to work at 150% capacity to finish the work. Find in how many days the faster one will finish the work alone.

(a) 15 days
(b) 25 days
(c) 30 days
(d) 40 days

1 Answer

7 votes

Final answer:

A can finish the work alone in (d) 40 days.

Step-by-step explanation:

To solve this problem, let's first assume that A can finish the work alone in x days. This means that in one day, A can complete 1/x of the work. We're given that when A works at 60% capacity, B has to work at 150% capacity to finish the work. This means that B's work rate is 1.5 times A's work rate.

Based on this information, we can set up the following equation:

(1/x) + (1.5/x) = 1/20

Simplifying the equation, we get:

2.5/x = 1/20

Solving for x, we find that x = 40. This means that A can finish the work alone in 40 days, so the answer is (d) 40 days.

User Simplethemes
by
8.3k points