Final answer:
Tilak, Mukesh, and Sonali work together for 2 days, then Tilak leaves and Mukesh and Sonali work for another 2 days before Mukesh departs. Sonali works alone for the last 3 days. The total time taken to complete the work is 7 days.
Step-by-step explanation:
To solve the problem of how many days it takes Tilak, Mukesh, and Sonali to complete the work, we need to calculate the work done by each member every day and then establish the total time taken for the completion of the work.
First, we find the individual work rates:
Tilak can complete the work in 10 days, so he does 1/10 of the work per day.
Mukesh can complete the work in 12 days, so he does 1/12 of the work per day.
Sonali can complete the work in 15 days, so she does 1/15 of the work per day.
When they work together for the first 2 days, they complete (1/10 + 1/12 + 1/15) of the work each day. Calculating the least common multiple (LCM) of 10, 12, and 15, which is 60, their combined work for each day is 6/60 + 5/60 + 4/60 = 15/60 or 1/4 of the work per day.
So in 2 days, they complete 2 * 1/4 = 1/2 of the work.
Now Tilak leaves, and Mukesh and Sonali work together for the next few days. Their daily work is now 1/12 + 1/15 = 9/60 or 3/20 of the work per day.
Mukesh then leaves 3 days before the completion, so we only have Sonali's rate at 1/15 per day to finish the remaining work. If x is the total number of days taken to complete the work, Sonali must have worked alone for (x - 2) - (x - 2 - 3) = 3 days.
Let's calculate the portion of work Sonali completes alone:
3 days * 1/15 per day = 3/15 = 1/5 of the work.
We now know that 1/2 of the work was completed in the first two days, and Sonali completes an additional 1/5 alone. Together, Mukesh and Sonali must have completed the remaining work in the period between.
The remaining work after the first two days is 1 - 1/2 = 1/2. The work Sonali completes alone is subtracted from this, leaving 1/2 - 1/5 = 5/10 - 2/10 = 3/10 of the work to be done by Mukesh and Sonali together.
At their combined rate of 3/20 per day, it takes them (3/10) / (3/20) = 2 days to complete the remaining 3/10.
Adding all the parts together, the task is completed in 2 (initial days with Tilak) + 2 (Mukesh and Sonali) + 3 (Sonali alone) = 7 days.
Therefore, the task took 7 days to complete, which is option C.