All of the following are possible conditions for an activity except which one?

a. it may have a predecessor(s) but no successor(s)
b. it may have a successor(s) but no predecessor(s)
c. it may have both predecessor(s) and successor(s)
d. it may not have a predecessor(s) or a successor(s)

1 Answer

2 votes

Final answer:

The correct answer is: d. It may not have a predecessor(s) or a successor(s). Within project management, activities in a project schedule must have predecessors, successors, or both. An activity without either is not possible, as it does not fit within a project sequence.

Step-by-step explanation:

The question provided relates to the concepts of project management and activity scheduling. Specifically, it discusses conditions that can be present for an activity within a project timeline. Let's analyze the options given:

  • An activity may have a predecessor(s) but no successor(s). This represents an activity that follows others, but is the last one in the project sequence.
  • An activity may have a successor(s) but no predecessor(s). This could be the first activity of a project, initiating the sequence.
  • An activity may have both predecessor(s) and successor(s). Most activities in a project will fall into this category, lying in the middle of the project sequence.
  • An activity may not have a predecessor(s) or a successor(s). This condition is not possible in a project as every activity is part of a sequence, even if it's the first or last activity; it still would have a successor or predecessor respectively.