Final answer:
RWP 3, option 3, is the action code that indicates a job has been deferred for materials, which helps in communicating job status and planning for task rescheduling.
Step-by-step explanation:
When dealing with Real Work Packaging (RWP) action codes in a job context, typically within the construction or maintenance industries, these codes serve to communicate the status of a job. In this specific instance, you're asking about an RWP action code that is used to indicate that a job has been deferred for materials.
The correct RWP action code for this situation is RWP 3. This means that when the workers or the management encounter a situation where they cannot proceed with the job because they are awaiting materials, they would mark the job with RWP 3 to indicate this particular deferral.
This ensures that all parties are aware of the job status, and allows for better planning and rescheduling of tasks once the materials become available.