Final answer:
In the plan phase of PDSA, implementing the plan should not be carried out; this step is reserved for the 'Do' phase. The correct steps in the plan phase include identifying the problem, developing a plan for improvement, and analyzing the results.
Step-by-step explanation:
As part of the plan phase of PDSA (Plan-Do-Study-Act), all of the following steps should be carried out except 'Implement the plan'. The plan phase of PDSA includes identifying the problem or opportunity, developing a plan for improvement, and analyzing the results. The actual implementation of the plan occurs in the subsequent 'Do' phase of the cycle. It's important not to confuse these phases, as each has its specific purpose within the continuous improvement process.
- Identify the problem or opportunity
- Develop a plan for improvement
- Analyze the results
Implementing the plan before properly planning and analyzing would be putting the cart before the horse, potentially leading to poor outcomes and inefficiency. The PDSA cycle helps ensure that improvements are based on careful planning and analysis.