Final answer:
The minimum design compressive strength of concrete is typically reached after 28 days of curing.
Step-by-step explanation:
The minimum design compressive strength of concrete is typically reached after a certain number of days of curing. This is known as the 28-day compressive strength. Therefore, the correct answer is option 4) 28 days.