Final answer:
The pump selector switch should be placed in the Flow-Through position when performing flushing operations on a Type III, IV, or V system.
Step-by-step explanation:
When performing flushing operations on a Type III, IV, or V system, the pump selector switch should be placed in the Flow-Through position. This position allows water to be drawn in through a lower valve and out through an upper opening, ensuring that 300% of the ballast tank capacity is pumped through.