What does a Sprint Burn Down Chart show?

User Claes
by
7.7k points

1 Answer

4 votes

Final answer:

A Sprint Burn Down Chart is a visual tool used in Agile project management to track the progress of work completed in a sprint. It shows the amount of work remaining versus the time available during the sprint. The goal is to have a smooth downward trend, indicating that the team is on track to complete all the work by the end of the sprint.

Step-by-step explanation:

A Sprint Burn Down Chart is a visual tool used in Agile project management to track the progress of work completed in a sprint. It shows the amount of work remaining versus the time available during the sprint. The chart typically has two axes: the vertical axis represents the amount of work remaining, while the horizontal axis represents time.

The chart starts at the top with the total amount of work estimated for the sprint and gradually goes down to zero as the work is completed. The goal is to have a smooth downward trend, indicating that the team is on track to complete all the work by the end of the sprint.

For example, let's say a software development team is working on a two-week sprint. At the beginning of the sprint, they estimate that there are 100 story points worth of work. As they complete tasks, they update the chart to reflect the remaining work.

If after one week they have completed 50 story points, the chart would show that there are still 50 story points remaining, and the trend would indicate that they are on track to finish all the work by the end of the sprint.