Final answer:
A Change Request is the document companies use to request new development, report problems, or ask for new features. It typically includes an introduction, problem discussion, solutions, and a conclusion to facilitate decision-making.
Step-by-step explanation:
The document that most companies have to request new development, report problems, or request new features within an existing project is a Change Request.A Change Request is a formal request that outlines the changes needed in a project or process, including the reasons for the requested changes and the impact they may have. It helps to ensure that any changes are properly documented, reviewed, and approved before being implemented. For example, if a software development company receives a request from a client to add new features to their existing software, they would use a change request document to manage the request and track the progress of the requested changes.Most companies utilize a specific kind of document to request new development, report problems, or ask for new features within an existing system.
The correct answer to this question is d) Change Request. A Change Request is a formal document that outlines a request for a change, including new development, fixes, or feature additions, and is typically used within the context of project management and IT development. It includes necessary details such as the scope of the change, its impact, and the benefits it will bring.Properly structured, a change request often follows a format similar to that found in a business proposal, starting with an introduction, followed by discussions of the problem, possible solutions, potential objections, and a conclusion with a recommendation. This ensures clarity and facilitates effective communication and decision-making within the company.