If the owner becomes aware of any fault or defect in the project, what should they do? According to which doc?

a) Notify the contractor - A201
b) Notify the architect - B101
c) Notify the engineer - A201
d) Notify the lawyer - B101

User Appukrb
by
6.7k points

1 Answer

7 votes

Final answer:

The owner should notify the architect about faults or defects in the project as per AIA Document B101. This allows for proper evaluation and correction of the issue.

Correct option is b) Notify the architect - B101

Step-by-step explanation:

When the owner becomes aware of any fault or defect in the project, they should promptly notify the architect according to the American Institute of Architects (AIA) Document B101, which is the Standard Form of Agreement Between Owner and Architect. This step is crucial as it allows the architect to evaluate the issue and determine the appropriate course of action. This procedure ensures that all parties involved in the construction process are informed and can collaborate to resolve the defect effectively.

This notification enables the architect to assess the issue promptly, facilitating a comprehensive understanding of the problem and allowing for the formulation of an appropriate resolution strategy. This collaborative approach ensures that all stakeholders are kept informed and can work together to address and rectify any defects efficiently. This proactive communication and problem-solving process contribute to the overall success and quality of the construction project.