Which of the following tools requires detailed instructions on how you want a group of resources deployed?

a. Gantt chart
b. SWOT analysis
c. Project plan
d. Resource allocation matrix

User Thosphor
by
8.5k points

1 Answer

5 votes

Final answer:

A Project plan requires detailed instructions on the deployment of resources for a project, unlike a Gantt chart, SWOT analysis, or a resource allocation matrix.

Step-by-step explanation:

The tool that requires detailed instructions on how you want a group of resources deployed is d. Project plan. A project plan is a formal document designed to guide the control and execution of a project. It includes detailed resource allocation, schedules, tasks, and outlines how resources should be assigned and utilized. Conversely, a Gantt chart (a) provides a visual timeline for tasks but does not offer detailed deployment instructions. A SWOT analysis (b) is a strategic planning tool used to identify strengths, weaknesses, opportunities, and threats, and is not related to resource deployment. Lastly, a resource allocation matrix (c) may indicate what resources are available and who is responsible for what, but it does not provide step-by-step deployment instructions like a project plan does.

User Stephendwolff
by
7.4k points