Final answer:
A Project plan requires detailed instructions on the deployment of resources for a project, unlike a Gantt chart, SWOT analysis, or a resource allocation matrix.
Step-by-step explanation:
The tool that requires detailed instructions on how you want a group of resources deployed is d. Project plan. A project plan is a formal document designed to guide the control and execution of a project. It includes detailed resource allocation, schedules, tasks, and outlines how resources should be assigned and utilized. Conversely, a Gantt chart (a) provides a visual timeline for tasks but does not offer detailed deployment instructions. A SWOT analysis (b) is a strategic planning tool used to identify strengths, weaknesses, opportunities, and threats, and is not related to resource deployment. Lastly, a resource allocation matrix (c) may indicate what resources are available and who is responsible for what, but it does not provide step-by-step deployment instructions like a project plan does.