How does a project manager demonstrate that they attend to the health of the team?

1) by holding team members accountable for non-performance
2) demonstrating their own personal energy and leading by example
3) allocate the leader's and team's time to monitoring team performance
4) regular discussions and check-ins with team members

User Luizmineo
by
8.0k points

1 Answer

1 vote

Final answer:

A project manager can demonstrate that they attend to the health of the team by holding team members accountable, leading by example, monitoring team performance, and having regular discussions and check-ins with team members.

Step-by-step explanation:

A project manager can demonstrate that they attend to the health of the team by:

  1. Holding team members accountable for non-performance: This shows that the project manager values the team's productivity and ensures that everyone is responsible for their work.
  2. Demonstrating their own personal energy and leading by example: When the project manager displays enthusiasm and a positive attitude, it can motivate the team members and create a healthy work environment.
  3. Allocating the leader's and team's time to monitoring team performance: By devoting time to monitoring team performance, the project manager can address any issues or concerns that may impact the team's well-being.
  4. Regular discussions and check-ins with team members: Engaging in regular discussions and check-ins allows the project manager to establish open lines of communication and provide support to team members.