Elijah is a warehouse production manager and has been assigned a complex project that might result in lengthy delays. In order to coordinate all aspects of the production process, Elijah has created a(n) ________ chart.

a. Gantt
b. FMS
c. PERT
d. ISO

1 Answer

6 votes

Final answer:

Elijah has created a Gantt chart to coordinate all aspects of a production process. Gantt charts are bar charts that illustrate a project schedule, which helps in managing complex projects and ensuring that every part of the process is well-organized and on track. The correct option is a.

Step-by-step explanation:

Elijah is a warehouse production manager and has been assigned a complex project that might result in lengthy delays. In order to coordinate all aspects of the production process, Elijah has created a Gantt chart. A Gantt chart is a type of bar chart that represents a project schedule.

It shows the start and finish dates of the various components and elements of a project. It is widely used in project management to illustrate the project's progress against established time periods and is particularly useful in managing the intricate details of production processes.

PERT (Program Evaluation and Review Technique) is also used in project management, particularly for the planning and coordination of tasks within a project.

Whereas ISO (International Organization for Standardization) is an entity that develops and publishes international standards, including those for quality management systems, but it is not a chart or tool for planning.

FMS (Flexible Manufacturing System) involves the use of robotics and computer-controlled machines in production but is not associated with planning charts either. The correct option is a.