Final answer:
True, When a task in-progress is rescheduled, a Gantt Chart does indeed show the delay as a split or gap, which visually indicates the pause in work.
Step-by-step explanation:
If you reschedule an in-progress task, the delay is shown as a split on the Gantt Chart. This statement is True.
A Gantt Chart is a project management tool that is used to represent the timing of tasks required to complete a project. When a task that is already in progress is rescheduled, the Gantt Chart reflects this change by showing a split or a gap in the bar that represents that task. This visually indicates the delay and the period during which the task was on hold before resuming.