The external predecessor and successor tasks in the task relationships between project files are sometimes called

a) Bridge Tasks
b) Link Tasks
c) Remote Tasks
d) Nexus Tasks

1 Answer

5 votes

Final answer:

The external predecessor and successor tasks in project management that indicate the relationships between different project files are commonly referred to as link tasks.

Step-by-step explanation:

In project management, dependencies between project files are denoted by link tasks. These tasks are essential for outlining the precedence and succession of multiple project elements. These tasks are critical in establishing dependencies across various projects or parts of a program. For instance, if one project's completion is contingent on the delivery of a component from another project, the completion task of the providing project is a predecessor link task to the dependent project's start-up task.