144k views
5 votes
You should save a project baseline when you have developed the project schedule as fully as possible.

a) True
b) False

User Pnv
by
8.3k points

1 Answer

5 votes

Final answer:

The statement is true; a project baseline should be saved when the project schedule is fully developed to serve as a reference point for future comparison and performance measurement.

Step-by-step explanation:

You should save a project baseline when you have developed the project schedule as fully as possible. The correct answer to this question is True. A project baseline is essentially a snapshot of the project's initial planned schedule, costs, scope, and other key variables which is used for comparison as the project progresses. It is important to establish a baseline for the project when the schedule is fully developed because it allows you to measure project performance and manage project scope effectively. It serves as a reference point to monitor and compare the actual work against the original plan as the project moves forward.

User Sanjo
by
8.9k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.