Final answer:
In Microsoft Project, entering actual work values automatically adjusts the remaining work on tasks, allowing for accurate tracking of project progress and aiding in completing tasks based on a Schedule of Work.
Step-by-step explanation:
By default, whenever you enter actual work values, Microsoft Project adjusts remaining work. This ensures that the project's schedule reflects real-world progress and informs you of the amount of work left to be completed for a given task. Microsoft Project automatically recalculates the remaining work when actual work is entered, which is crucial for accurately tracking project progress and making necessary adjustments to keep the project on track.For successful project management, it's essential to adhere to a Schedule of Work, which outlines dates of availability and due dates. Planning your time accordingly based on the schedule provided can lead to an organized approach to completing tasks. Remaining vigilant with the Activities Overview and making timely entries of actual work into Microsoft Project is part of the broader strategy of working on the course throughout the week.