Only a(n) _________ can have a remaining work or duration value.

a) Summary Task
b) Subtask
c) Milestone
d) Assignment

User Robertwb
by
8.0k points

1 Answer

2 votes

Final answer:

The correct answer is d) Assignment, as assignments have work or duration values in project management.

Step-by-step explanation:

The answer to the question 'Only a(n) _________ can have a remaining work or duration value.' is d) Assignment. In project management terminology, specific assignments made to team members or resources are what can have remaining work or a duration value. A summary task is a collection of subtasks and typically reflects the total values of its subtasks rather than having its own independent duration. A subtask is a division of a summary task and has its own work and duration values. A milestone marks a significant point or event in a project and is generally set to have zero duration.

User Carson
by
8.9k points

Related questions

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.