Final answer:
In MS Project, when actual work values are entered, the software automatically adjusts the remaining work to maintain the total work estimate for a task.
Step-by-step explanation:
When you enter actual work values in MS Project, the software adjusts the remaining work automatically by default. This ensures that the total work for a task remains constant unless you specify otherwise. For example, if a task was originally estimated at 10 hours of work and you enter 3 hours of actual work, MS Project will automatically calculate 7 hours of remaining work. The software is designed to help project managers efficiently track and manage project schedules and resources, automatically recalculating and adjusting as actual data is entered.