You can create a(n) ______________ between projects if the completion of a task in one project has an effect on a task in another project.

a) Interlink
b) External Dependency
c) Cross-Project Link
d) Shared Connection

1 Answer

1 vote

Final answer:

The correct answer is cross-project link, which means establishing a connection between tasks in different projects where one task is contingent upon the other, known as an external dependency in project management.

Step-by-step explanation:

You can create a cross-project link between projects if the completion of a task in one project has an effect on a task in another project. This concept is often referred to as an external dependency, where the start or finish of a particular task is dependent on the start or completion of another task outside of the current project's scope. Understanding and managing such dependencies is a key aspect of project management as they can significantly impact the project schedule and resource allocation.

User Jiwan
by
9.3k points