151k views
3 votes
Adjusting the aspects of the project schedule, such as cost, duration, and scope, to achieve a desired project schedule result is known as __.

a) Resource Leveling
b) Baseline Optimization
c) Project Tuning
d) Schedule Compression

1 Answer

0 votes

Final answer:

Schedule compression is the process of adjusting project aspects for a desired schedule result.The correct answer is d) Schedule Compression.

Step-by-step explanation:

Schedule compression is the process of adjusting the aspects of the project schedule, such as cost, duration, and scope, in order to achieve the desired project schedule result. This may involve shortening the project duration, allocating more resources to critical tasks, or reevaluating the project scope to meet the desired timeline.

For example, if a construction project is falling behind schedule, the project manager might decide to compress the schedule by adding more workers or increasing the work hours to complete the project on time.

User Omar Fayad
by
7.7k points