The amount the finish date on a task can be delayed before the completion of the project will be delayed is known as __.

a) Total Slack
b) Free Slack
c) Project Slack
d) Critical Slack

User Cjk
by
7.5k points

1 Answer

4 votes

Final answer:

Option a)Total Slack is the amount of time a task can be delayed without delaying the project's completion date.

Step-by-step explanation:

The amount the finish date on a task can be delayed before the completion of the project will be delayed is known as Total Slack(option a).

Total Slack is the total amount of time that a task can be delayed without affecting the project's overall completion date. It represents the flexibility in the project schedule.

For example, if a project has a total slack of 5 days, it means that any task can be delayed by up to 5 days without affecting the project's completion date.