A(n) __ determines how a resource's work on a task is scheduled over time.

a) Resource Calendar
b) Work Contour
c) Assignment Calendar
d) Resource Allocation

1 Answer

5 votes

Final answer:

A work contour determines the scheduling of a resource's work on a task over time, relating to efficient resource allocation and labor supply within the constraints of a 24-hour day. It helps manage variations in demand and resource availability in project management. The correct answer is 'Work Contour.

Step-by-step explanation:

A work contour determines how a resource's work on a task is scheduled over time. In project management, work contouring is the process of assigning different levels of resource efforts at various stages of the task. It is part of the broader topic of resource allocation, a fundamental issue all societies face due to the scarcity of resources and the need to distribute these resources effectively. This concept ties into the labor supply, highlighting the time constraint each individual has, summing up to 24 hours a day to be divided between work and leisure.

The importance of work contouring lies in its ability to ensure efficient use of labor and resources. By tailoring the amount of work and effort across different periods, project managers can address fluctuations in demand, scheduling conflicts, and variations in resource availability. It's a strategic tool that aligns with the three basic economic questions that all societies must answer, underpinning the notion of resource allocation and the ever-present problem of scarcity.