Final answer:
The correct answer is b) Summary Task. The term refers to values like duration and work that show combined information of all subtasks within a larger project.
Step-by-step explanation:
The values of a consolidated project, such as duration and work, represent the rolled-up Summary Task values of the inserted projects. The term 'Summary Task' in the context of project management software, such as Microsoft Project, refers to a row that displays the combined values of its subtasks. Duration, work, costs, and other aggregated data are shown on the summary task to provide a high-level overview of the project's progress and requirements. This consolidation allows project managers to see the total duration and work effort required for a complete section of the project or the entire project, reflecting all individual tasks that are being executed simultaneously.