When you adjust the remaining work on a task, MS Project __ distributes the work

a) Equally among all resources
b) Proportionally based on resource costs
c) Based on resource availability
d) Randomly among all tasks

1 Answer

4 votes

Final answer:

MS Project adjusts the remaining work on a task based on the availability of the resources assigned to it, considering their workload and schedules.

Step-by-step explanation:

When you adjust the remaining work on a task in MS Project, it distributes the work based on resource availability. This means that the software looks at the schedules of the assigned resources and balances the workload according to when each resource is available to work on the task. It takes into account the current workload of resources, their calendars, and any other constraints that might be in place.