Only a(n) __ can have a remaining work or duration value.

a) Summary task
b) Milestone
c) Subtask
d) Inactive task

1 Answer

7 votes

Final answer:

Only a subtask can have a remaining work or duration value, as it represents a specific portion of a project, unlike summary tasks, milestones, or inactive tasks(option c).

Step-by-step explanation:

Only a subtask can have a remaining work or duration value(option c).

In project management, a subtask represents a portion of a larger task or project and can have its own specific duration or amount of work needed for completion. On the other hand, a summary task aggregates the information from its subtasks and does not itself have a duration value that can be 'remaining' since it is simply a roll-up of its subtasks. Milestones are typically set to have zero duration because they signify the achievement of a significant point or event in a project, and inactive tasks are tasks that are not currently active in the project schedule.

User MichaelH
by
8.3k points

Related questions

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.