Which dialog box is used to record actual work done on a task?

a) Task Information
b) Resource Sheet
c) Update Project
d) Work Breakdown Structure (WBS)

User Mataniko
by
8.5k points

1 Answer

6 votes

Final answer:

The Update Project dialog box is used to record actual work done on a task.

Step-by-step explanation:

Which dialog box is used to record actual work done on a task?

The correct answer is c) Update Project.

The Update Project dialog box in project management software is used to record the actual work done on a task. It allows you to enter actual start and finish dates, % complete, hours worked, and any remaining work.

By updating the project with actual work done on a task, you can track progress, compare it with the planned schedule, and make adjustments if necessary.