One way of interpreting SPI (schedule performance index) is schedule __.

a) Acceleration
b) Efficiency
c) Delay
d) Variance

1 Answer

2 votes

Final answer:

The correct interpretation of SPI (Schedule Performance Index) is efficiency. SPI is a measure used in project management to assess the efficiency of meeting project deadlines.

Step-by-step explanation:

The correct interpretation of SPI (Schedule Performance Index) is efficiency. SPI is a measure used in project management to assess the efficiency of meeting project deadlines. The Schedule Performance Index is a measure of the efficiency of time usage in the context of project management. If the SPI is greater than 1, it indicates that the project is ahead of schedule, while an SPI less than 1 indicates that the project is behind schedule. It is calculated by dividing the earned value (EV) by the planned value (PV) of the project. If SPI is greater than 1, it indicates that the project is ahead of schedule, while an SPI less than 1 suggests that the project is behind schedule.

User Roman Shelkford
by
8.2k points