Final answer:
A Sprint Planning Meeting comprises the WHAT-Meeting, where the team selects work from the product backlog, and the HOW-Meeting, where the team plans how to accomplish these tasks. Thus, the correct answer is d) WHAT-Meeting and HOW-Meeting.
Step-by-step explanation:
The components of a Sprint Planning Meeting include both the WHAT-Meeting and the HOW-Meeting. During the WHAT-Meeting part, the team selects the work they believe they can complete during the sprint from the product backlog. The HOW-Meeting focuses on breaking down the selected items into tasks and devising a plan for how to complete those tasks. Thus, the correct answer to which meetings are part of a Sprint Planning Meeting is d) WHAT-Meeting and HOW-Meeting.