Final answer:
The Sprint Retrospective Meeting aims to reflect on the past sprint's positive and negative aspects and to define actionable improvements for future sprints. The correct answer is d) A, B, C.
Step-by-step explanation:
The goal of the Sprint Retrospective Meeting is to provide a time for the team to reflect on the most recent sprint and identify what went well, what didn't, and how processes can be improved. This meeting is not just about focusing on the negative issues, but also the positive aspects of the sprint, in order to create a balanced view of the team's performance. Most importantly, the Sprint Retrospective is about defining actionable suggestions for the team to implement in future sprints to continuously improve their workflow and productivity. So, the answer to the student's question would be d) A, B, C, since it encompasses reflecting on positive and negative issues as well as defining actionable suggestions to improve performance.