The Scrum Product Owner is in the progress of creating a release plan. Which information should he include or show?

a) Estimated user stories
b) Assignments of user stories to sprints
c) Release dates
d) Assumptions and constraints
e) All of the above

User Artak
by
7.5k points

1 Answer

5 votes

Final answer:

The Scrum Product Owner should include estimated user stories, assignments of user stories to sprints, release dates, and assumptions and constraints in a release plan. Therefore, the correct answer is 'e) All of the above'.

Step-by-step explanation:

When a Scrum Product Owner is in the progress of creating a release plan, they should include a comprehensive set of information that covers various aspects of the release. This includes:

  • Estimated user stories to provide a clear picture of the functionality that will be developed.
  • Assignments of user stories to sprints to outline how the work will be distributed over the different iterations.
  • Release dates to offer a timeframe for when features are expected to be available to the end-users.
  • Assumptions and constraints to acknowledge any external factors that may impact the release plan.

The correct answer to what information should be included or shown in a release plan would therefore be e) All of the above.