How to develop job scheduling by four dispatching rules: FCFS,

EDD, ODD, and SPT? Which rule works the best for a scheduling?

1 Answer

3 votes

Final answer:

To develop job scheduling by the four dispatching rules: FCFS, EDD, ODD, and SPT, you would need to understand each rule and how it works. The rule that works best for job scheduling can depend on various factors such as the nature of the jobs, their priorities, and the overall objectives of the scheduling. Each rule has its pros and cons and may be more suitable for specific scenarios.

Step-by-step explanation:

To develop job scheduling by the four dispatching rules: FCFS, EDD, ODD, and SPT, you would need to understand each rule and how it works.

FCFS stands for First-Come, First-Served, which means that jobs are scheduled in the order they arrive. EDD stands for Earliest Due Date, where jobs are scheduled based on their due dates, with the one closest to the current time being prioritized. ODD stands for Oldest Due Date, where jobs are scheduled based on their due dates, with the one furthest from the current time being prioritized. SPT stands for Shortest Processing Time, where jobs are scheduled based on their processing times, with the one that takes the least time being prioritized.

The rule that works best for job scheduling can depend on various factors such as the nature of the jobs, their priorities, and the overall objectives of the scheduling. Each rule has its pros and cons and may be more suitable for specific scenarios. There is no one-size-fits-all answer, and it would require careful analysis and testing to determine which rule works best in a given context.