Given the following information, complete the forward and backward pass to compute the early start, late start, early finish, late finish, and activity slack. Identify the critical path. Show ALL of your working to get the points.

a) True
b) False

1 Answer

7 votes

Final answer:

The forward and backward pass are techniques used in project management to determine task times and identify the critical path.

Step-by-step explanation:

In project management, the forward and backward pass are techniques used in critical path method (CPM) to determine the early start, late start, early finish, late finish, and activity slack of tasks in a project. The forward pass starts from the beginning of the project and calculates the earliest possible start and finish times for each task, while the backward pass starts from the end of the project and calculates the latest possible start and finish times. The critical path is the sequence of tasks that have zero slack, meaning any delay in the critical path will delay the project's completion. By completing the forward and backward pass calculations, you can identify the critical path and assess the impact of any schedule changes.

User Tanishalfelven
by
7.5k points