Calculate the average lateness using the FCFS rule for the following jobs awaiting processing at a work center. Select the correct response: 13.5 12 12

1 Answer

5 votes

Final answer:

To calculate the average lateness using the FCFS rule, add up the lateness values and divide by the total number of values.

Step-by-step explanation:

To calculate the average lateness using the FCFS (First-Come, First-Served) rule, we need to find the mean of the lateness values. In this case, the lateness values are 13.5, 12, and 12.

Step 1: Add up all the lateness values: 13.5 + 12 + 12 = 37.5

Step 2: Divide the sum by the total number of values: 37.5 ÷ 3 = 12.5

Therefore, the average lateness using the FCFS rule for the given jobs is 12.5 minutes.