While performing the "3.3 Remove dollies, winches, and cables from both locations" work package, an accident occurred and work took 6 days longer than originally scheduled. Update the work package based on this change. Which of the following is true? Note: Before you proceed to the next question, close the file without saving changes, then reopen it to return to the original schedule. OR: change the task duration back to 1 day. Group of answer choices There was no impact on the remaining tasks "4.10 Reattach house" was no longer on the critical path The overall project deadline was delayed by 6 days "4.7 Pull second half out of the lake dollies" was forced to start 6 days later than scheduled

User Wesww
by
7.3k points

1 Answer

4 votes

Final answer:

The accident caused the "3.3 Remove dollies, winches, and cables from both locations" work package to take 6 extra days. The overall project deadline was delayed by 6 days.

Step-by-step explanation:

Based on the information provided, the accident caused the "3.3 Remove dollies, winches, and cables from both locations" work package to take 6 days longer than originally scheduled. Therefore, the work package needs to be updated to reflect this change.



Following the accident, the overall project deadline was delayed by 6 days. This means that the project will now be completed 6 days later than initially planned.



It is important to update the schedule and task durations accordingly to reflect this delay. However, we cannot determine from the information given whether "4.10 Reattach house" is still on the critical path or if "4.7 Pull second half out of the lake dollies" was forced to start 6 days later than scheduled.