A large field can be prepared for planting by 5 workers in 24 days. How many workers (of equal ability) are needed to finish the field in 15 days?

User Nluo
by
8.3k points

1 Answer

5 votes

Final answer:

To determine the number of workers needed to complete the field preparation in 15 days instead of 24, we use the concept of inverse proportionality and calculate that 8 workers are required.

Step-by-step explanation:

The question of how many workers are needed to finish preparing a large field in 15 days instead of 24 days by 5 workers is a problem of inverse proportionality. To solve this, we can set up a proportion where work done is constant: Number of workers × Number of days = constant. In this case, we have 5 workers taking 24 days, which gives us 5 × 24 = 120 worker-days. To find the number of workers needed for 15 days, we set up the equation x × 15 = 120, where x is the number of workers needed. Solving for x gives us x = 120 / 15, resulting in x = 8. Therefore, 8 workers of equal ability are needed to finish the field in 15 days.

User LastBye
by
7.8k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.