166k views
1 vote
At an auto shop, six jobs are currently in queue. Round your answer to two decimal places. Using the shortest processing time scheduling approach, what is the average inventory of jobs in the system?

User Shamas
by
8.8k points

1 Answer

4 votes

Final answer:

To find the average inventory of jobs in the system using the shortest processing time scheduling approach, calculate the sum of the processing times of all jobs in the queue and divide it by the number of jobs.

Step-by-step explanation:

To find the average inventory of jobs in the system using the shortest processing time scheduling approach, we need to consider the time it takes to complete each job as well as the number of jobs in the queue.Given that there are six jobs currently in the queue, we can calculate the average inventory using the formula:Average Inventory = (Processing Time of Job 1 + Processing Time of Job 2 + ... + Processing Time of Job 6) / Number of Jobs Since we don't have the processing times of each job, we can't provide a specific answer, but you can calculate it by substituting the actual processing times into the formula and rounding the result to two decimal places.

User Eirc
by
8.3k points