Final answer:
The lateness of job B would be 0 weeks.
Step-by-step explanation:
The lateness of a job can be calculated by subtracting the job's due time from its completion time. According to the table, the processing time for job B is 1.02 weeks and the due time is 2 weeks. Since the job is processed using the earliest-due-date rule, it will be completed within its due time. Therefore, the lateness of job B is 0 weeks.