Processing times and due dates for five jobs... Processing times and due dates for five jobs are shown in the table below. Assume the jobs are processed using the earliest-due-date rule. Job Processing time (weeks) Due time (weeks) A B 1 1.02 8 2 WP> D E 5 1.0 1 4 8 12. What would be the lateness of job B?

User Mcgraphix
by
8.2k points

1 Answer

4 votes

Final answer:

The lateness of job B would be 0 weeks.

Step-by-step explanation:

The lateness of a job can be calculated by subtracting the job's due time from its completion time. According to the table, the processing time for job B is 1.02 weeks and the due time is 2 weeks. Since the job is processed using the earliest-due-date rule, it will be completed within its due time. Therefore, the lateness of job B is 0 weeks.