215k views
2 votes
If 9 builders take 24 days to complete a project, how many builders would be needed to finish the same project in 18 days?

User Aleth
by
8.0k points

1 Answer

3 votes

Answer:

9 builders = 24 days

? = 18 days

therefore, 9×24/18

= 12 builders

therefore, proved

User Rbrayb
by
8.2k points

No related questions found