144k views
4 votes
The 4 people in your crew each spent 4 hours laying sod. How many person- hours is this?

A. 4
B. 8
C. 12
D. 16
E. 20

User Musthafa
by
8.8k points

1 Answer

2 votes

Final answer:

The total person-hours spent by a crew of 4 people each working for 4 hours is 16 person-hours. This is calculated by multiplying the number of people by the hours each person worked, resulting in 4 x 4 = 16.

"the correct option is approximately option D"

Step-by-step explanation:

The question involves calculating total person-hours spent on a task, which is a basic mathematical concept. To answer this, you simply multiply the number of people by the number of hours each person worked. In this scenario, we have 4 people who each spent 4 hours laying sod. So, the calculation is 4 people x 4 hours/person = 16 person-hours. Therefore, the correct answer is D. 16.

To illustrate further, person-hours is a way of measuring the amount of work done by a group of people over a certain period. If one person works for one hour, that's one person-hour of work. When four people work for one hour, that's four person-hours because four times the work is being done in that hour compared to just one person.

Likewise, if one person works for four hours, that too is four person-hours. In this case, every person in the group of four is contributing four person-hours, so the total work done by the entire group is 4 people x 4 hours each = 16 person-hours total, making it a simple arithmetic problem often encountered in middle school math.

User Kal
by
8.2k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories