kalid can complete a piece of work in 18 days while natnael and ali can complete the same work in 12 days and 6 days respectively. kalid worked for two days then natnael joined her for 2 ore days and finally ali joined them and the wor was completed by the three of them. how long did the work take?

User Thompson
by
8.1k points

1 Answer

2 votes

Answer:

6

Explanation:

kalid 18)6

ali 6/6

natneal 12/6