148k views
3 votes
Machine A takes 2 hours to paint a car alone, and machine B takes 3 hours alone. If they work together for 1 hour and then machine B breaks down, how much longer will it take machine A to finish the job?

(A) 1 hour
(B) 2 hours
(C) 3 hours
(D) 4 hours

User Azhidkov
by
7.6k points

1 Answer

5 votes

Final answer:

After 1 hour of working together, Machine A and Machine B complete 5/6 of the job. Machine B breaks down, and Machine A alone takes an additional 1/3 hour to finish the remaining 1/6 of the job. None of the provided options are correct.

Step-by-step explanation:

Machine A takes 2 hours to paint a car alone, and Machine B takes 3 hours to paint a car alone. To figure out how much work each machine does per hour, we calculate their rates of work. Machine A's rate is 1/2 car per hour, and Machine B's rate is 1/3 car per hour. When they work together, they can paint 1/2 + 1/3 = 3/6 + 2/6 = 5/6 cars per hour. After working together for 1 hour, they complete 5/6 of the job, leaving 1/6 of the job unfinished.

Now, we need to calculate how much longer it will take for Machine A to finish the remaining 1/6 of the job alone. Since Machine A's rate is 1/2 car per hour, it will take Machine A 1/6 divided by 1/2, which equals 1/6 * 2/1 = 2/6 = 1/3 hour to finish the job. Therefore, it will take Machine A an additional 1/3 hour to finish painting the car on its own after Machine B breaks down. To answer the question, none of the options (A) 1 hour, (B) 2 hours, (C) 3 hours, (D) 4 hours accurately reflect the calculated time of 1/3 hour.

User Shoren
by
7.6k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories