99.2k views
5 votes
A company has been commissioned to excavate a 30-meter deep well. For the 1st excavated meter, they charge 6 euros, and each successive meter, as the depth increases, costs 2.5 euros more than the previous one. How much will the completed job cost?

a. 1640.50
b. 1630.50
c. 1267.50
d. 1620.50

1 Answer

6 votes

Final answer:

To find the total cost of excavating a 30-meter deep well with increasing costs per meter, we calculate the sum of an arithmetic series. The cost starts at 6 euros and increases by 2.5 euros per meter. The final cost is 1267.5 euros, making option c the correct answer.

Step-by-step explanation:

The question requires us to calculate the total cost of excavating a 30-meter deep well where the cost increases by 2.5 euros for each additional meter after the first. The cost for the first meter is 6 euros. The total cost can be found using an arithmetic series where the first term is 6 euros and the common difference is 2.5 euros.

To calculate the total cost, we will use the following formula for the sum of an arithmetic series: S = n/2 × [2a + (n-1) × d], where:

  • S is the sum of the series,
  • n is the number of terms,
  • a is the first term,
  • d is the common difference.

Here, n is 30 (since the well is 30 meters), a is 6 (cost of the first meter), and d is 2.5 (increase in cost per meter).

Calculating the cost:

S = 30/2 × [2×6 + (30-1)×2.5] = 15 × (12 + 72.5) = 15 × 84.5 = 1267.5 euros.

Therefore, the completed job will cost 1267.5 euros, which makes option c. 1267.50 the correct answer.

User Nickornotto
by
8.4k points